Project Timeline

Project Status

This project is under active development. We will be working throughout the process to consult with local community members and stakeholders about the project. The feedback received, in conjunction with the results of environmental assessments, will inform the project design.

Work is underway to further investigate the wind resource in the area, and to conduct environmental studies across the project site.

Project Timeline

2019

Site Identification

Early project development and wind monitoring

2019

2020-2021

Wind Resource Assessment

Installation of wind monitoring equipment to measure wind speeds across the proposed project area

2020-2021

March 2021

Environmental Studies Commence

Detailed environmental studies are conducted throughout 2021 and 2022. As part of this process, we will assess the visual and ecological impact of the wind turbines. The results will be incorporated into the project’s development application

March 2021

Mid 2022

Submit EPBC Act Referral

We will refer the project to the Australian Department of Agriculture, Water and the Environment (DAWE) for review and approval

Mid 2022

Late 2022

Submit Development Application

We will submit a development application to the State Assessment and Referral Agency (SARA) seeking consent under State Code 23: Wind Farm Development

Late 2022

Mid 20223

Development Approval

State development consent expected

Mid 20223

Mid 2023

EPBC Approval

Federal EPBC approval expected

Mid 2023

Late 2023

Grid Connection

An Offer to Connect expected

Late 2023

Early 2024

Financial Close

Project secures financing, and contracts for construction commence

Early 2024

Mid 2024

Begin Construction

Construction at site expected to begin. This process will take approximately 24 months

Mid 2024

Contact Us

We're here to answer questions, provide updates and receive your feedback